Resource Assignments

There are options on the Resource Assignments page of the Integration Wizard for retrieving labor that you can use when linking with a resource loaded schedule.

These options are as follows:

  • Budgeted Quantity: Values stored in the budgeted units (Target_qty) field are imported when importing a budget. Values stored in the Pending Remaining Units (Remain_qty) field are imported when importing forecast data.
  • Budgeted Cost: Values stored in the budget cost are imported when selecting to import from a budget. Values stored in the remaining cost are imported when you select a forecast.